The existing building has previously been used as a small-scale data centre for multiple end users, as well as temporary accommodation. During the survey, it was in minimal use by limited staff for office activities, taking place from the reception area only. The purchase of the site was under consideration…
Our commission involved the Technical Due Diligence assessment of this existing site, including the following:
Technical Due Diligence
- Overview on current grid supply
- Explore grid capacity expansion:
- 5MW
- 8.6MW
- 10MW
- Explore fibre upgrade feasibility
- Desktop proximity survey on:
- Electric
- Fibre
- Gas
- Water
- District Heating / Cooling
- Utility survey BSI (PAS 128)
- Topographical survey
“The JB Associates team visited site to assess the existing utility infrastructure and coordinate the required specialist surveys. Upon return to the UK extensive desktop research and analysis was conducted, to further explore existing connections and potential upgrade feasibility, resulting in a comprehensive report on findings”.